Cargo questions cover the current operation, the plan and the people: who is on duty, what they were briefed on and whether officers hold the right endorsements.

Do this before the inspector arrives: Brief the duty AB on the current cargo operation.

What the inspector wants to see

Questions inspectors ask about Cargo

What is checked for IGS operation and PV valve testing?
IGS operation, PV valve test records and the type approval certificate of the PV valve test kit.
When must the fixed O2 analyser be calibrated before starting the IG/N2 system?
Within 24 hours before starting the system.
How should the vapour manifold be marked and fitted?
Two 10 cm red bands with 'VAPOUR' stencil; cruciform bollard (600 mm high), pad eye (SWL 15 t) and Panama lead in line; threaded stud bolt (1/2 inch dia, 1 inch protruding).
What is expected for deck-mounted cargo heaters?
Testing and operation records, and the company testing requirement for periods when heating is not used.
Are cargo tank isolating valves maintained and tested?
Each isolating valve should be maintained and tested. Missing records were flagged.
How do you test the loadicator, and what variation is allowed?
Run test conditions and compare the results; the notes allow 2-5% variation.

There are 98 Cargo questions in NilObs, with spaced repetition so the ones you miss come back. Practise them free.

Real Cargo observations, and how to avoid them

From 69 de-identified observations in SIRE 2.0, CDI and pre-vetting reports from 2025 and 2026. Wording paraphrased; ship, crew and company names removed.

A CCR table set an initial loading velocity of 1 m/s at the 6 or 8 inch tank inlets but did not give the matching loading rates.
Avoid it: Convert inlet velocity limits into m3/h for each inlet size so the initial loading rate is clear.
SIRE 2.0 · Chapter 8 Cargo & ballast systems · Human observation
The main deck safety inspection checklist did not include checking bonding wires.
Avoid it: Add bonding straps on cargo pipelines and hoses to the deck inspection routine.
SIRE 2.0 · Chapter 5 Safety management · Process observation
A cargo pump's local hydraulic pressure gauge on deck had no needle.
Avoid it: Replace broken gauges promptly using the spares carried.
SIRE 2.0 · Chapter 2 Certification & documentation · Hardware observation
The nitrogen line was pressure tested at 2.4 bar although its working pressure was 0.2 bar and the recommended test pressure 0.24 bar.
Avoid it: Confirm the correct test pressure for each line before testing and record it.
SIRE 2.0 · Chapter 8 Cargo & ballast systems · Process observation
Interviewee did not know the recommended test pressure for the nitrogen line.
Avoid it: Know the working and test pressures of the lines you are responsible for.
SIRE 2.0 · Chapter 8 Cargo & ballast systems · Human observation
Alarm settings on the cargo tank secondary venting pressure sensors did not match company requirements for the discharge mode in use.
Avoid it: Adjust tank pressure alarm set points for each operation (loading, discharging with IG) per the company table.
SIRE 2.0 · Chapter 8 Cargo & ballast systems · Hardware observation
The CCR officer had not set the required tank pressure alarm settings for discharging with inert gas; corrected before the inspector left.
Avoid it: Make alarm set point changes part of the pre-discharge checklist.
SIRE 2.0 · Chapter 8 Cargo & ballast systems · Human observation
The cargo and ballast valve test record had no provision to check that local and remote valve position indicators agreed.
Avoid it: When testing hydraulic valves, compare local and remote position indicators and record the result.
SIRE 2.0 · Chapter 8 Cargo & ballast systems · Process observation

Who answers for Cargo

Chief Officer, Pumpman, Marine Superintendent, Port Captain, Vetting Manager / Superintendent. NilObs picks the questions and the daily drill for your role.

Rehearse Cargo before your next inspection.
A 5-minute daily drill for your role, an AI inspector that grades your answers, and live industry updates. Free to start.
Start free

Other topics

ECDIS9 observationsRadar4 observationsUKC3 observationsPassage planning5 observationsGMDSS10 observationsAlarm & power-fail tests3 observationsEquipment tests vs PMS23 observationsDocuments & SMS51 observationsRest hours & drills17 observationsDefect reporting29 observationsWatchkeeping16 observationsSteering2 observationsLSA & FFA31 observationsEngine room50 observationsPIQ accuracy46 observationsPermits & RA11 observationsEmergency equipment43 observationsGas testing & enclosed space61 observationsPPE & personal safety21 observationsPollution prevention27 observationsSecurity & cyber11 observationsTraining & certificates25 observationsHull & condition31 observationsMooring & access59 observations